Regarding the article titled “Miały być kryształy, jest klops” (“How crystals have turned into abject failure”) published by the Gazeta Wyborcza daily on December 18th 2023, we would like to clarify and correct certain aspects that were falsely represented in the publication concerning a facility construction project executed for Grupa Azoty.
First of all, it is important to emphasise that Grupa Azoty is the aggrieved party in this case.
- The alleged “expanded scope of the project work”
mentioned in the article has been the subject of a long-standing court dispute
between Grupa Azoty S.A. and Cenzin Sp. z o.o. The project in question was to
be executed under a lump-sum turnkey contract between Grupa Azoty S.A. and
Cenzin Sp. z o.o. Biprokwas Sp. z o.o. was not a party to that contract.
- Contrary to what the article claims, there is no
documentation to prove that “shortly after the contract was signed, Grupa Azoty
sought changes to its provisions regarding the scope of the construction work”. There is no documentation, either, to substantiate
the claim that Grupa Azoty S.A. demanded the facility to be designed “so that a second process line could be installed at some point in the future”. Hence we
believe there is nothing to suggest that the initial scope of the project work
was later “expanded”. Our position was affirmed by the first instance
court’s decision dismissing the claim filed by Cenzin sp. z o.o.
- It is crucial to note that the construction of
the desulfurisation unit was halted by the contractor, Cenzin (Biprokwas was
its subcontractor).After unsuccessful attempts lasting more than a month to negotiate the contractor’s return to work, Grupa Azoty S.A., acting in
accordance with the relevant contractual clauses, formally withdrew from the
contract.
- The contractor's pretext for halting the work was a claim for additional payment over and above the contract sum. The contractor claimed that such additional cost was
due to the “expanded scope of the project work”, which, as clarified earlier,
was not demanded by Grupa Azoty S.A., as supported by the first instance
court’s ruling.
- The article suggests that an amendment to the contract
was to be signed, but in reality the contractor proposed an amendment when the
contract was already at an advanced stage, and the amendment was to
concern past occurrences. For obvious reasons, Grupa Azoty S.A. did not agree
to that proposal.
- It is important to highlight that a similar unit was
being constructed by Biprokwas Sp. z o.o. for another large chemical
company in Poland. Based on publicly available information, the unit had
significant defects hindering the boiler’s operation due to performance
issues and the need to use specific feedstock with a very low sulfur content.
The same defects were identified in the unit constructed for Grupa Azoty S.A.
under the contract with Cenzin Sp. z o.o. by Biprokwas.
- We further wish to state that the article’s
claim regarding alleged infringement of copyrights, rights to technology and
know-how by Grupa Azoty S.A. is equally false. Specifically, the use of
magnesite instead of lime as a sorbent is a widely known and commonly used
method which does not require any specific licences, as the patent protection
of the magnesium-based wet desulfurisation process has already expired.
Grupa Azoty’s decision to issue this statement has
been prompted by the slanderous nature of Gazeta Wyborcza’s publication.